Permitting: recovering from a difficult first launch

Permitting's first release was not well received, with an NPS of about −32. By working directly with the users who had the most concerns, we brought it to about +32.

Role
Designed the tool and led its redesign
Context
Sphere's first permit management tool
Outcome
NPS about −32 → about +32

The ask

Create Sphere's first permit management tool. Until then, subcontractors had managed permits on their own.

The challenge

  • Limited access during design. Early requirements were gathered without design in the room, and I worked from business cases rather than direct conversations with the divisions.
  • A difficult launch. About 44% of surveyed employees were detractors and 12% were promoters. Users felt the tool imposed a way of working that didn't reflect their reality.

The approach

  • Listening to those with the most concerns. Collaborative design sessions that made our decision-making visible.
  • Mapping the process as it really worked. A service design document showing how permitting would run in person, on paper.
  • Making it visual. The workflow, its impact, and the importance of accuracy, shown visually rather than in project-management terms.

Outcomes

NPS −32 → +32
after the redesign, about 44% of respondents were promoters and 12% detractors

Figures are approximate, from internal surveys.

What didn't go to plan

The first release. In hindsight, I should have advocated more strongly for direct access to the divisions early on. It was a period of leadership change, and I chose to be cautious.

Turning point

The service design document. It turned a disagreement about software into a shared picture of the actual work, and many of the tool's critics became contributors.

What I learned

Design developed at a distance from users struggles, even when the screens are sound. Involving the people who do the work from the start makes the difference.